Mission/Silo Rd

Fort Hunter Liggett

Project Date
2018
Project Location
Fort Hunter Liggett
Project Owner
USACE
Project Description

This roadway re-alignment project at Mission and Nacimiento-Fergusson Roads included new access to the Green Bridge and Low Water Crossing, installation of 60" CSP and concrete box culverts, retaining walls, full-depth reconstruction, and asphalt paving. Construction through a culturally significant area required protective measures and special handling.